Work experience: 32 years. Development of design and layout solutions for steam, make-up water, condensate, cooling water, oil pipelines, chemically demineralized water lines, etc. Equipment layout.

Major objects:

  • The Zaporizhzhya NPP. Reconstruction.
  • The South-Ukraine NPP. Reconstruction.
  • ”Obra” Thermal Power Plant. Blocks No.1, 2. With a capacity of 50 MWth. Reconstruction.
  • The «Bushehr» NPP. Block No.1. New construction.
  • Thermal Power Plant-4, Ulaanbaatar,  (Mongolia). Extension with the installation of turbo generator Т-120/130-130-8МО.
  • Construction of an energy complex for a sulfuric acid plant in the village of Zhanakorgan.
  • “Ilyich Iron and Steel Works” PJSC, Mariupol. Reconstruction with new construction of GCPs for BF No. 2,4,5 cast houses and stockhouse.
  • “МК “Аzovstal” PJSC, Mariupol. Electrical generator unit. PK 1. Reconstruction of converter gas cleaning system for the converter shop.